KHS Wear Part Packages: Turning 1,750 Hours Into a Plan

Maintenance Guides · 8 min read · 2026-11-07

A running-hour interval is only useful when it reaches the calendar

KHS describes wear-part packages supplied at fixed intervals and gives 1,750 operating hours as a published example. That number is not a promise that every machine or every part lasts the same time. It is a planning input. Your maintenance team must translate it into shifts, production windows, consumption and stock. At continuous operation, 1,750 hours is about 73 days. At 16 hours per day and five days per week, it is about 21.9 weeks, or roughly six months. The same nominal interval creates very different purchase dates on different lines. Start with the hours actually run, then check the result against your failure history.

Why the calendar can give the wrong answer

A calendar date ignores whether the machine ran 2,000 hours or 6,000 hours in the year. It also hides product changes, more frequent washdown, extra format changes and a new shift pattern. A wear package that is late on a high-hour line can turn a planned stop into an air shipment and an emergency repair. Use the published example as a reference point and label it clearly as an example. Do not present it as a fixed KHS service interval for a machine you have not identified. The working plan should show hours, part consumption, inspection results and the next stop window.

1. Convert 1,750 hours into your operating calendar

For continuous running, divide 1,750 by 24. The result is approximately 72.9 days. For a five-day schedule at 16 hours per day, divide 1,750 by 80 hours per week. The result is approximately 21.9 weeks. For a 24-hour, seven-day line, the date is close to ten and a half weeks. Write the calculation next to the machine record. Then replace the assumptions with actual running hours from the counter. If a line stops for holidays or runs at a lower shift load, the calendar date moves. If a seasonal line runs longer during peak demand, the date comes earlier. The purpose is to trigger a review before the hour count is reached. Lead time, customs, inspection and the next planned stop all need space. A package that arrives on the day of the interval is already late if the line must be opened that morning.

2. Define what belongs in the wear-part package

Typical wear items may include seals, scraper blades, guide rails, suction cups, cutting blades, small springs and filters. The exact list must follow the machine and the position record. These parts change with contact, friction, contamination or repeated cycling, so a package can reduce routine ordering. Bearings and drive components normally belong to condition-based maintenance unless your own data supports a planned change. A bearing with stable vibration and temperature should not be replaced simply because a small seal is due. Conversely, a bearing with metal dust, heat or noise should not be protected by the calendar label “not in the package.” Separate the package into consumption items and condition items. This makes the purchase easier to explain and prevents the team from treating every component as a fixed-interval part. For packaging-line support, Conveying parts, Pneumatics, Accessories and the Full parts catalogue can help group the request by subsystem.

3. Build the first package from twelve months of records

If there is no usable OEM list, export the last twelve months of work orders and stores issues. Group parts by machine, position and failure mode. Mark whether each item was replaced after inspection, after a breakdown or as part of a format change. Remove duplicates caused by different descriptions for the same part. Calculate consumption per 1,000 running hours. Then separate normal consumption from a one-time failure. If one scraper was damaged by a foreign object, do not let that event set the package quantity. If a seal was replaced every two months on the same position, the history is meaningful even if the old work orders use inconsistent names. Set an initial package quantity with a review date. For example, a package might contain the observed average plus one line-stop contingency for a critical, low-cost seal. That is an internal planning rule, not a universal engineering fact. Record why the quantity was chosen and revise it after the next cycle.

4. Compare package cost with emergency cost

Use a transparent example, not a claimed site result. Suppose a planned package costs 1,200 currency units, while an emergency shipment costs 250 units in freight, 300 units in handling and 1,000 units for a short stop. Those figures are placeholders, not market prices. The point is to show the structure: part cost, freight, delay and the probability of a second intervention. If a package includes parts that never wear, its excess stock reduces the benefit. If a low-cost part can stop the line, keeping one extra piece may be rational. Show finance the hour count, the planned stop date, the package contents and the assumption behind the contingency quantity. A list with no failure history looks like a discretionary purchase; a record tied to line hours is easier to review.

5. Split the package across one stop window

The package should reduce the number of times the same machine is opened. Group the work by access and contamination control. Replace seals and scraper blades while the relevant guard is already open. Inspect rails, suction cups and small springs in the same area. Keep bearings and drives on the inspection list unless evidence supports replacement. Create a stop sheet with the part, position, quantity, inspection result and sign-off. Put the replacement parts next to the machine in the sequence they will be used, but keep sealed product-contact parts protected. If a part is not used, return it to stores with its identity and reason. Unused parts are data for the next package decision. Do not open two separate stops because purchasing delivered a package in two waves. Order early enough for inspection and count verification. The exact lead time depends on the part and supplier, so put the required date in the RFQ instead of relying on the interval alone.

6. Keep a record that can improve the next decision

At minimum, record the running-hour counter, date, product or format, part position, old part condition, new part identity, reason for replacement and remaining stock. Add the stop duration when the line is opened. For each part, mark whether it was used, returned, damaged before installation or found unnecessary. After the stop, compare actual consumption with the planned package. A part that is always returned may belong in condition inspection. A part that repeatedly runs out before the next interval needs a shorter trigger or a larger package. A part that fails earlier only on one product may need a product-specific record rather than a global interval.

What to replace, and what to replace at the same time

Part Symptom it causes Replace together with Typical trigger
Seal Leak, loss of pressure or contamination risk Inspect mating surface and spring Hour trend or visible damage
Scraper blade Poor cleaning or residue carryover Check holder and gap Edge wear or hardened residue
Guide rail Product instability or misalignment Inspect wheel, cam and fasteners Thickness loss or impact
Suction cup Missed pick or label transfer loss Check vacuum line and filter Hardening, cracks or low grip
Cutting blade Torn cut or incomplete separation Inspect counterpart and clearance Dull edge or chipped tip
Small spring Slow return or intermittent motion Inspect seat and moving part Corrosion or permanent set
Bearing or drive Noise, heat or vibration Condition inspection, not automatic pack Trend or failure evidence

Field checklist

Read the actual running-hour counter and write the date of the reading. Convert 1,750 hours using the line's real hours per day and days per week. Pull twelve months of work orders and stores issues for the machine. Group entries by part position and remove duplicate descriptions. Separate planned wear replacements from breakdowns and foreign-object damage. Calculate consumption per 1,000 running hours for each repeated item. Mark each item as package, condition check or one-off repair. Tie the package to the next planned stop and allow time for receiving inspection. Count every part before the stop and protect product-contact components. Record what was installed, returned, damaged or found unnecessary. Review the package after the stop and change the next quantity from evidence.

When to stop repairing and overhaul

A wear package is not a substitute for an overhaul when the same area shows multiple interacting faults. Stop repeating small part changes when guide wear has changed alignment, a bearing has heat or vibration, a drive has backlash, or the frame and mounting surfaces no longer hold position. Those conditions can destroy a new seal or blade quickly. Use the package to prepare the small, predictable work. Use condition evidence to decide whether the machine needs an engineering inspection. If the stop will already expose the assembly, combine the inspection with the planned replacements. That reduces repeat access while keeping condition-based decisions separate from a copied hour number.

FAQ

What if the line runs fewer than 1,750 hours per year?

Do not force an annual purchase if the machine has not reached the hour trigger and the parts do not have a shelf-life reason. Track actual hours, inspect the package items and review at the next planned stop. Elastomers and some chemicals may need separate storage controls, so use the part's condition and storage requirement as an additional trigger.

Can I split the wear-part package?

Yes, if the split follows a real stop window, subsystem or risk priority. Keep the parts that protect product quality and prevent a stop together when access is shared. Splitting only to reduce the purchase line can create two interventions and higher labor or freight cost.

Are third-party wear parts equivalent?

A third-party item may be a compatible replacement or aftermarket equivalent when its fit, function, material and service condition are confirmed. Do not treat all third-party parts as interchangeable. Send the position, old part, material requirement and failure data, then compare the proposed item before ordering.

How do I explain the purchase to finance?

Show the running-hour calculation, the twelve-month consumption record, the next stop date and the cost assumptions. Separate predictable wear items from condition-based components. A simple table that links each item to a machine position and a replacement reason is stronger than a generic “spares” request.

What happens if we skip one interval?

The risk depends on the part and the machine condition. A low-risk item may be inspected and carried forward. A seal, blade or guide that protects product or alignment may fail before the next window. Record the decision, inspect the item and keep a contingency part when the consequence of failure is high. Need a specific part? Send the machine model, the position number and two photos of the part — we quote within one business day. → Send your parts list


All brand names, trademarks and model numbers mentioned are the property of their respective owners and are used for identification and reference purposes only. We supply compatible aftermarket replacement parts and are not an authorized distributor or representative of Krones AG or KHS GmbH.